Xtrend Garage Conversions: a Garage Conversion in 69 Hours
When considering a garage conversion, we are often asked many questions. 2 of the most popular questions are: “how long does a garage conversion take?” and “what is involved in a garage conversion?”
The following is a case study on a typical garage conversion broken down into stages and hours to give an answer to those most commonly asked questions. The following does not take into account drying times and other variables, but is intended to give you a small insight in the various stages of a typical garage conversion.
The average garage conversion from commencement to completion takes between 1.5 and 2 weeks... This one took 69 hours, so without further ado:
- Once appointed we check the status of planning permission requirements (usually not required) and submit the building notice to our nominated building inspectors - Active Approved Inspectors. We also begin to order materials and source a suitable brick match for your approval.